Construction of an eight (8) storey building plus two (2) levels of basement carparking, comprising eighty-four (84) apartments and reduction in car parking requirements. |
(Source: Darebin Council, 申请编号: D/251/2011) |
|
2012年05月23日 |
Construction of an eight (8) storey building plus two (2) levels of basement carparking, comprising eighty-four (84) apartments and reduction in car parking requirements. |
(Source: Darebin Council, 申请编号: CON/197/2012) |
|
2012年05月24日 |
Construction of an eight (8) storey building plus two (2) levels of basement carparking, comprising eighty-four (84) apartments and reduction in car parking requirements. |
(Source: Darebin Council, 申请编号: CON/195/2012) |
|
2012年07月05日 |
Apartment Development - Stage 1: Demolition of Existing Building Only |
(Source: Darebin Council, 申请编号: 49208/2014/1) |
|
2013年07月19日 |
Construction of an eight (8) storey building plus two (2) levels of basement carparking, comprising eighty-four (84) apartments and reduction in car parking requirements. |
(Source: Darebin Council, 申请编号: CON/281/2013) |
|
2013年07月26日 |
Amendment to condition 4 of the permit, in association with the construction of an eight (8) storey building plus two (2) levels of basement carparking, comprising eighty-four (84) apartments and reduction in car parking requirements. |
(Source: Darebin Council, 申请编号: D/251/2011/A) |
|
2014年06月30日 |
Construction of an eight (8) storey building plus two (2) levels of basement carparking, comprising eighty-four (84) apartments and reduction in car parking requirements. |
(Source: Darebin Council, 申请编号: CON/273/2014) |
|
2014年07月28日 |
Apartment Development - Stage 2: Basement Retention and Bulk Excavation only Excluding Works along the North Boundary |
(Source: Darebin Council, 申请编号: 49208/2014/2) |
|
2014年08月05日 |
Apartment Development - Stage 3: Remainder of Basement Retention and Bulk Excavation |
(Source: Darebin Council, 申请编号: 49208/2014/3) |
|
2014年09月05日 |
Construction of an eight (8) storey building plus two (2) levels of basement carparking, comprising eighty-four (84) apartments and reduction in car parking requirements. |
(Source: Darebin Council, 申请编号: D/251/2011/B) |
|
2014年10月01日 |
Apartment Development - Stage 4: Basement 2 Structural Works Only |
(Source: Darebin Council, 申请编号: 49208/2014/4) |
|
2014年11月11日 |
Apartment Development - Stage 5: Structural Works up to & Including Ground Floor Slab only |
(Source: Darebin Council, 申请编号: 49208/2014/5) |
|
2015年01月06日 |
Apartment Development - Stage 6 Structural works up to & including 4th floor slab |
(Source: Darebin Council, 申请编号: 49208/2014/6) |
|
2015年02月17日 |
84 lot subdivision |
(Source: Streamlined Planning through Electronic Applications and Referra, 申请编号: S063759T) |
|
2015年02月19日 |
Eight-four (84) lot subdivision as shown on the plans accompanying the application |
(Source: Darebin Council, 申请编号: D/77/2015) |
|
2015年02月24日 |
Apartment Development - Stage 7: Remainder of Structural Works & Fire Services |
(Source: Darebin Council, 申请编号: 49208/2014/7) |
|
2015年03月26日 |
Apartment Development - Stage 8: Remainder of Works |
(Source: Darebin Council, 申请编号: 49208/2014/8) |
|
2015年06月15日 |
Construction of an eight (8) storey building plus two (2) levels of basement carparking, comprising eighty-four (84) apartments and reduction in car parking requirements. |